Utility-Scale Solar and Storage Baseline

Three solar and storage sites, each tied to an interconnection date set by the utility.

Owner
Confidential
Region
U.S. Southwest
Market
Power & Renewables
Our role
Baseline development
Size
3 sites · 600 MW
Delivery
EPC
Duration
22 months
Completed
2025
The challenge

What was at stake.

The EPC schedule treated interconnection as a single milestone. In reality, the utility's substation work, protection studies and testing each had their own timeline, and any slip moved the commercial operation date.

Schedule22 monthsCompleted 2025
20242025
Start
2024
Finish
2025
Duration
22 mo
Our role

What we did.

Beck Franklin's role: baseline development. We advise and measure; the contractor builds.

01

Utility work in logic

We added the utility's substation work, studies and testing to the baseline as linked activities.

02

Site by site

Each site had its own path to commercial operation, so one site's delay did not hide behind another.

03

Module and battery supply

Module and battery deliveries were tracked against installation need dates.

04

Monthly critical path

The owner received a monthly report on the driving path at each site.

Results

What the team delivered.

3 of 3Sites energized on plan
600 MWBrought online
22Months, notice to proceed to operation
MonthlyCritical path report

Interconnection is not one milestone. It is the utility's schedule inside yours, and we built it in.

Energy scheduler, Beck Franklin
Illustrative image
Power & Renewables

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.