Oil, Gas & Chemicals · U.S. Gulf Coast

Chemical Plant Turnaround Schedule

A 38-day chemical plant turnaround tracked by shift and handed back a day early.

Owner
Confidential
Region
U.S. Gulf Coast
Market
Oil, Gas & Chemicals
Our role
Turnaround scheduling
Size
38-day outage
Delivery
EPC
Duration
10 months
Completed
2024
The challenge

What was at stake.

Every outage day is lost production. The scope included vessel inspections, exchanger bundles and a catalyst change, each with discovery risk. The previous turnaround had run eight days over.

Schedule10 monthsCompleted 2024
2024
Start
2024
Finish
2024
Duration
10 mo
Our role

What we did.

Beck Franklin's role: turnaround scheduling. We advise and measure; the contractor builds.

01

Scope freeze

We worked with operations to freeze scope early and schedule every work order in detail.

02

Shift-level schedule

The turnaround was scheduled by the shift, with critical path work staffed around the clock.

03

Discovery allowance

Inspection results were built in as decision points, with planned responses for likely findings.

04

Twice-daily updates

Progress was updated twice a day and reviewed at each shift change.

Results

What the team delivered.

1 dayEarly handback
38Days planned outage
2Updates every day
0Unplanned scope added late

A turnaround is won in planning. We froze the scope early and scheduled every shift.

Turnaround scheduler, Beck Franklin