Acute Care Bed Tower Baseline Rebuild

An eleven-story acute care tower whose first contractor baseline promised a finish the logic could not reach.

Owner
Confidential
Region
U.S. Southeast
Market
Healthcare
Our role
Baseline development
Size
11 stories · 260 beds
Delivery
CM at-risk
Duration
34 months
Completed
2025
The challenge

What was at stake.

The submitted baseline met the owner's opening date, but it did so with 140 open ends, hard constraints on the last six floors and medical equipment shown as a single milestone. Accept it, and every later delay would be argued against a schedule that was never real.

Schedule34 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
34 mo
Our role

What we did.

Beck Franklin's role: baseline development. We advise and measure; the contractor builds.

01

Logic test first

We ran a full logic and constraint check on the submitted XER and showed the owner which dates were held up by constraints, not by work.

02

Rebuilt with the CM

Working with the CM's scheduler, we rebuilt the floor-by-floor sequence, interior rough-in flow and the medical equipment chain in P6.

03

Activation in logic

Licensing inspections, equipment acceptance and staff move-in were tied to the construction finish instead of floating free.

04

A baseline to measure by

The rebuilt baseline was accepted and used as the yardstick for every monthly update through turnover.

Results

What the team delivered.

On dateFirst patients admitted as planned
140Open ends closed in the baseline
34Months measured on one baseline
260Beds turned over together

A baseline that meets the date only through constraints is a forecast nobody can use. We rebuilt it so the date came from the work.

Lead scheduler, Beck Franklin
Illustrative image
Healthcare

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.