Illustrative image
Healthcare · U.S. Midwest

Inpatient Unit Renovation Delay Analysis

A six-floor inpatient renovation where concealed conditions and approval delays stacked up and both sides claimed the time.

Owner
Confidential
Region
U.S. Midwest
Market
Healthcare
Our role
Time impact analysis
Size
6 inpatient floors
Delivery
Design-Bid-Build
Duration
22 months
Completed
2024
The challenge

What was at stake.

Asbestos above ceilings, slow infection control approvals and a late fire alarm redesign all hit within the same quarter. The contractor requested a large time extension. The owner needed to know which events actually moved the finish and which were absorbed by float.

Schedule22 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
22 mo
Our role

What we did.

Beck Franklin's role: time impact analysis. We advise and measure; the contractor builds.

01

Contemporaneous updates

We used the monthly updates already on record as the basis, so the analysis reflected what the team knew at the time.

02

Fragnets per event

Each event was modeled as a fragnet and inserted into the update before it, then measured against the driving path.

03

Concurrency tested

Where owner and contractor delays overlapped, we separated them by floor and by date so each party saw its share.

04

Plain-language report

The findings went to the owner as a short report with one chart per event and a recommended position.

Results

What the team delivered.

5Events analyzed with fragnets
2Events found to drive the finish
22Months of updates reviewed
SettledExtension agreed without dispute

Not every delay moves the finish. The analysis showed which ones did, floor by floor, and that ended the argument.

Forensic scheduler, Beck Franklin
Illustrative image
Healthcare

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.