Project controls · Construction scheduling · Project management consulting Know what’s driving your project CareersPartnersMediaProgram RatesData date
Illustrative image
Healthcare · U.S. Northeast

Academic Medical Campus Integrated Master Schedule

A research building, a clinical tower and a parking structure, delivered by two contractors toward one campus activation date.

Owner
Confidential
Region
U.S. Northeast
Market
Healthcare
Our role
Integrated master schedule
Size
3 buildings · 1.1M SF
Delivery
CM at-risk
Duration
60 months
Status
In progress · 2028
The challenge

What is at stake.

Each contractor reports its own schedule on its own calendar and coding. Utility tie-ins, a shared crane zone and a common loading dock link the projects, but no single schedule shows how a slip on one moves the others. Leadership was reading three reports that did not agree.

Schedule60 monthsIn progress · finish 2028
202320242025202620272028
Today
Start
2023
Planned finish
2028
Time elapsed
58%
Our role

What we are doing.

Beck Franklin's role: integrated master schedule. We advise and measure; the contractor builds.

01

One integrated schedule

We built a summary-level integrated master schedule in P6 that links the three projects at shared milestones and interfaces.

02

Common coding

Both contractors map their activities to a common WBS and milestone set, so updates roll up without retyping.

03

Interface register

Every handoff between projects is logged with an owner and a need date, and reviewed in the monthly update.

04

One page for leaders

A single executive page shows each project's forecast against the activation date and the top three drivers.

Results

Where it stands.

3Projects on one master schedule
46Interfaces tracked by owner
MonthlyIntegrated update to leadership
60Months from start to activation

Three good schedules can still add up to a bad forecast. The integrated view shows the owner where the campus actually stands.

Program controls lead, Beck Franklin
Illustrative image
Healthcare

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.