Academic Medical Campus Integrated Master Schedule
A research building, a clinical tower and a parking structure, delivered by two contractors toward one campus activation date.
- Owner
- Confidential
- Region
- U.S. Northeast
- Market
- Healthcare
- Our role
- Integrated master schedule
- Size
- 3 buildings · 1.1M SF
- Delivery
- CM at-risk
- Duration
- 60 months
- Status
- In progress · 2028
What is at stake.
Each contractor reports its own schedule on its own calendar and coding. Utility tie-ins, a shared crane zone and a common loading dock link the projects, but no single schedule shows how a slip on one moves the others. Leadership was reading three reports that did not agree.
What we are doing.
Beck Franklin's role: integrated master schedule. We advise and measure; the contractor builds.
One integrated schedule
We built a summary-level integrated master schedule in P6 that links the three projects at shared milestones and interfaces.
Common coding
Both contractors map their activities to a common WBS and milestone set, so updates roll up without retyping.
Interface register
Every handoff between projects is logged with an owner and a need date, and reviewed in the monthly update.
One page for leaders
A single executive page shows each project's forecast against the activation date and the top three drivers.
Where it stands.
Three good schedules can still add up to a bad forecast. The integrated view shows the owner where the campus actually stands.
Program controls lead, Beck Franklin
Illustrative imageMore from Buildings.
All Buildings
Healthcare · 2025Acute Care Bed Tower Baseline RebuildU.S. Southeast · Baseline development · 34 months
Healthcare · In progressDiagnostic Imaging Pavilion Cost ForecastU.S. Pacific Northwest · Cost forecasting · 24 months
Healthcare · 2024Inpatient Unit Renovation Delay AnalysisU.S. Midwest · Time impact analysis · 22 months