Power & Renewables · U.S. Midwest

Gas Peaking Plant Schedule Review

Four peaking units promised for a capacity year, with the EPC schedule reviewed for the owner each month.

Owner
Confidential
Region
U.S. Midwest
Market
Power & Renewables
Our role
Owner's schedule review
Size
4 units · 400 MW
Delivery
EPC
Duration
28 months
Status
In progress · 2027
The challenge

What is at stake.

Missing the capacity year means penalties and lost revenue. Turbine delivery, gas pipeline connection and transmission upgrades all sit on or near the critical path, and the EPC's monthly report does not show the owner how close each is.

Schedule28 monthsIn progress · finish 2027
202520262027
Today
Start
2025
Planned finish
2027
Time elapsed
53%
Our role

What we are doing.

Beck Franklin's role: owner's schedule review. We advise and measure; the contractor builds.

01

Monthly review

We review each EPC schedule update for logic, progress and lost float.

02

Three key paths

Turbine delivery, gas connection and transmission upgrades are tracked as separate paths.

03

Capacity date check

Every review ends with a clear view on whether the capacity date is at risk.

04

Owner briefings

The owner's leadership receives a one-page briefing each month.

Results

Where it stands.

MonthlyReview and briefing
3Driving paths tracked
400 MWOf peaking capacity
28Months to commercial operation

The owner has one date that matters. Each review tells them plainly whether it is safe.

Owner's scheduler, Beck Franklin