Transit Station Accessibility Program

Elevators and ramps at twelve stations that stay open to riders throughout construction.

Owner
Confidential
Region
U.S. Northeast
Market
Transportation
Our role
Integrated master schedule
Size
12 stations
Delivery
CM/GC
Duration
40 months
Status
In progress · 2026
The challenge

What is at stake.

Each station needs track outages, power isolations and temporary passenger routes. Outages are scarce and shared with other programs. If a station misses its outage, it can wait months for the next one.

Schedule40 monthsIn progress · finish 2026
2023202420252026
Today
Start
2023
Planned finish
2026
Time elapsed
97%
Our role

What we are doing.

Beck Franklin's role: integrated master schedule. We advise and measure; the contractor builds.

01

Master schedule

We built an integrated master schedule with every station and every planned outage.

02

Outage readiness

Each outage has a readiness checklist reviewed two weeks before: materials, crews, permits and inspections.

03

Station by station

Progress is reported station by station, so a problem at one does not hide in the program average.

04

Outage forecasting

We forecast outage needs a year ahead so the agency can request them early.

Results

Where it stands.

12Stations on one schedule
64Track outages planned
0Outages lost to readiness
40Months for the full program

On a transit program, the outage is the critical path. We plan around every one.

Transit scheduler, Beck Franklin