Freight Rail Yard Expansion Delay Analysis

A rail yard expansion where both the owner and the contractor claimed the same five months.

Owner
Confidential
Region
U.S. Midwest
Market
Transportation
Our role
Windows delay analysis
Size
14 new tracks
Delivery
Design-Build
Duration
28 months
Completed
2024
The challenge

What was at stake.

Late signal design, wet ground and changes to track geometry all landed in the same year. The contractor sought an extension and costs; the owner sought liquidated damages. The dispute was heading to a hearing.

Schedule28 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
28 mo
Our role

What we did.

Beck Franklin's role: windows delay analysis. We advise and measure; the contractor builds.

01

Windows analysis

We divided the project into windows between updates and measured the critical path change in each.

02

Cause by window

Each window's delay was assigned to its cause using the contemporaneous record.

03

Concurrency

Where owner and contractor delays overlapped, the analysis showed both and how they interacted.

04

Settlement support

The findings were presented in a short report and used in settlement talks.

Results

What the team delivered.

5 monthsDelay split by cause
14Windows analyzed
SettledWithout a hearing
28Months on the project record

When both sides claim the same months, the record decides. A windows analysis let it speak clearly.

Forensic scheduler, Beck Franklin
Illustrative image
Transportation

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.