Terminal Concourse Renovation Phasing

An eighteen-gate concourse renovated in phases while flights kept operating.

Owner
Confidential
Region
U.S. Southeast
Market
Aviation
Our role
Phasing schedule and TIA
Size
18 gates
Delivery
CM at-risk
Duration
36 months
Completed
2025
The challenge

What was at stake.

Gates could leave service only in an order agreed with the airlines, and each phase needed temporary walls, passenger routing and systems cutovers. Two phases were hit by owner design changes, and the contractor sought time for both.

Schedule36 monthsCompleted 2025
2022202320242025
Start
2022
Finish
2025
Duration
36 mo
Our role

What we did.

Beck Franklin's role: phasing schedule and tia. We advise and measure; the contractor builds.

01

Phasing schedule

We built a phasing schedule with each gate's out-of-service and return dates as constraints.

02

Cutovers in logic

Fire alarm, baggage and IT cutovers were tied to the phases that needed them.

03

TIA for changes

Each design change was assessed with a time impact analysis before the extension was agreed.

04

Airline updates

Airport operations received a monthly look-ahead of gate closures based on the schedule.

Results

What the team delivered.

18Gates returned to service
6Phases, all in agreed order
2TIAs agreed without dispute
5 weeksAhead of the original finish

At an airport the gate sequence is a contract with the airlines. The schedule had to honor it phase by phase.

Aviation scheduler, Beck Franklin