Airfield Taxiway Reconstruction Recovery

Two taxiways rebuilt in a short paving season that lost three weeks to a wet spring.

Owner
Confidential
Region
U.S. Mountain West
Market
Aviation
Our role
Schedule recovery
Size
2 taxiways · 9,000 ft
Delivery
Design-Bid-Build
Duration
20 months
Completed
2024
The challenge

What was at stake.

Paving could not happen below a set temperature, and the season ended with the first frost. After the spring rain, the contractor's schedule showed the finish slipping past the season, which would have left a taxiway closed through winter.

Schedule20 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
20 mo
Our role

What we did.

Beck Franklin's role: schedule recovery. We advise and measure; the contractor builds.

01

Paving path first

We rebuilt the remaining schedule around the paving path, the work that had to finish before frost.

02

Extended shifts

Recovery options with added shifts and a second paving crew were costed and compared.

03

Daily look-ahead

A daily look-ahead tied paving to weather forecasts and closure permits.

04

Weekly reporting

The airport received a weekly report on recovered days and remaining float.

Results

What the team delivered.

3 weeksRecovered before frost
2Taxiways reopened before winter
9,000 ftOf taxiway rebuilt
20Months, design to reopening

The season was fixed. The recovery plan put every paving day where the weather allowed it.

Recovery scheduler, Beck Franklin