Project controls · Construction scheduling · Project management consulting Know what’s driving your project CareersPartnersMediaProgram RatesData date
Illustrative image
Water & Wastewater · U.S. Southwest

Raw Water Pipeline and Pump Station Baseline

Thirty-one miles of raw water pipeline and two pump stations, scheduled from easements and long-lead pumps outward.

Owner
Confidential
Region
U.S. Southwest
Market
Water & Wastewater
Our role
Baseline development
Size
31 miles · 2 pump stations
Delivery
CM at-risk
Duration
32 months
Completed
2025
The challenge

What was at stake.

When construction started, a quarter of the easements were still being negotiated and the pumps had a long fabrication lead time. The draft schedule assumed continuous pipe laying from one end to the other.

Schedule32 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
32 mo
Our role

What we did.

Beck Franklin's role: baseline development. We advise and measure; the contractor builds.

01

Easements in logic

Every unsigned easement became an activity with a need date, so pipe crews were never scheduled onto land the utility did not control.

02

Spreads by reach

The line was split into reaches with their own crews, so open land could proceed while easements closed.

03

Pump chain

Pump submittals, fabrication, factory testing and delivery were scheduled as one chain to the station start-up.

04

Monthly critical path

The driving path was reported monthly, with easement status shown beside it.

Results

What the team delivered.

On planFirst water delivered
31Miles scheduled by reach
58Easements tracked to need dates
32Months, notice to proceed to start-up

A pipeline schedule that ignores easements is a guess. We made every parcel an activity with a date.

Infrastructure scheduler, Beck Franklin
Illustrative image
Water & Wastewater

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.