Project controls · Construction scheduling · Project management consulting Know what’s driving your project CareersPartnersMediaProgram RatesData date
Illustrative image
Water & Wastewater · U.S. Mid-Atlantic

Biosolids Digester Upgrade Recovery

A digester upgrade running seven months behind with a regulatory deadline on the horizon.

Owner
Confidential
Region
U.S. Mid-Atlantic
Market
Water & Wastewater
Our role
Schedule recovery
Size
4 digesters
Delivery
Design-Bid-Build
Duration
26 months
Completed
2024
The challenge

What was at stake.

Tank rehabilitation found more corrosion than expected, and a mixing system redesign held up two digesters. The utility faced a permit compliance date, and the contractor's schedule still showed the original finish with no explanation of how.

Schedule26 monthsCompleted 2024
202220232024
Start
2022
Finish
2024
Duration
26 mo
Our role

What we did.

Beck Franklin's role: schedule recovery. We advise and measure; the contractor builds.

01

Status from the field

We walked each digester with the contractor and rebuilt the remaining work from what was actually in place.

02

Recovery options

Three recovery sequences were modeled, including bringing one digester online early to meet the compliance date.

03

Decision in two weeks

The utility and contractor chose an option within two weeks, and the recovery schedule became the new baseline.

04

Weekly tracking

Progress against the recovery plan was reported weekly until the first digester was back in service.

Results

What the team delivered.

On timeCompliance date met
7 monthsDelay at the start of recovery
3Recovery options modeled
4Digesters back in service

Recovery starts with an honest count of the remaining work. The schedule that existed did not have one.

Recovery scheduler, Beck Franklin
Illustrative image
Water & Wastewater

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.