Food & Beverage · U.S. Midwest

Plant-Based Protein Facility Schedule Review

A new food plant with a product launch date fixed before the design was complete.

Owner
Confidential
Region
U.S. Midwest
Market
Food & Beverage
Our role
Schedule review and updates
Size
260,000 SF
Delivery
Design-Build
Duration
22 months
Completed
2024
The challenge

What was at stake.

The launch date was public. The design-builder's schedule assumed equipment would arrive as ordered and that sanitary finishes could overlap with equipment setting. Neither assumption was tested.

Schedule22 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
22 mo
Our role

What we did.

Beck Franklin's role: schedule review and updates. We advise and measure; the contractor builds.

01

Baseline review

We tested the baseline for logic, equipment lead times and the overlap of finishes and equipment setting.

02

Equipment tracker

Each major equipment package was tracked from purchase order to factory test to delivery.

03

Monthly reviews

Each update was reviewed for logic changes, lost float and progress that did not match the field.

04

Owner briefings

The owner received a short monthly briefing with the three items most likely to move the launch.

Results

What the team delivered.

On planFirst production run
22Equipment packages tracked
22Monthly updates reviewed
3Top risks briefed each month

When the launch is public, the schedule has to be tested in private first. That is what each review was for.

Senior scheduler, Beck Franklin