Government & Civic · U.S. West

Municipal Service Center Schedule Recovery

A city service center and fleet yard that had to be ready before the lease on the old yard ran out.

Owner
Confidential
Region
U.S. West
Market
Government & Civic
Our role
Schedule recovery
Size
160,000 SF · fleet yard
Delivery
Design-Bid-Build
Duration
22 months
Completed
2023
The challenge

What was at stake.

Steel was late, and the fuel island needed a new permit. The schedule showed the finish two months after the lease end, which would have left city vehicles with nowhere to go.

Schedule22 monthsCompleted 2023
20222023
Start
2022
Finish
2023
Duration
22 mo
Our role

What we did.

Beck Franklin's role: schedule recovery. We advise and measure; the contractor builds.

01

Lease date first

We set the lease end as the target and identified the minimum the city needed to move in.

02

Partial occupancy

Fleet parking, fueling and the maintenance bays were scheduled to finish first, ahead of offices.

03

Permit tracking

The fuel island permit was tracked weekly with the agency.

04

Move plan

The city's move was scheduled with the contractor's finish, so crews and vehicles moved in stages.

Results

What the team delivered.

Before lease endFleet moved in
2 monthsDelay at the start of recovery
3Move stages, each on time
22Months, start to occupancy

The city did not need every room finished. It needed the yard. The recovery plan put that first.

Recovery scheduler, Beck Franklin