Stadium Seating Bowl Rebuild Controls
A sixty-thousand-seat bowl rebuilt between seasons, with event dates the team cannot move.
- Owner
- Confidential
- Region
- U.S. Southwest
- Market
- Sports & Entertainment
- Our role
- Schedule risk and cost forecasting
- Size
- 60,000 seats
- Delivery
- CM at-risk
- Duration
- 36 months
- Status
- In progress · 2027
What is at stake.
Demolition, precast seating and the new concourse have to fit between seasons. Material prices and precast plant capacity are uncertain, and the owner needs to know both the likely finish and the likely final cost.
What we are doing.
Beck Franklin's role: schedule risk and cost forecasting. We advise and measure; the contractor builds.
Risk-based dates
We built a risk model that gives P50 and P80 dates for each season's handback.
Cost forecast
A monthly cost forecast ties each scope package to the schedule and to its contingency draw.
Precast tracking
Precast production at the plant is tracked against erection need dates every week.
Event constraints
Every scheduled event is a hard constraint, with readiness reviews before each.
Where it stands.
The events are fixed, so the risk has to be measured. We report both the date and the confidence behind it.
Risk and cost lead, Beck Franklin
Illustrative imageMore from Buildings.
All Buildings
Sports & Entertainment · 2025Collegiate Arena Off-Season RenovationU.S. Midwest · Phasing and progress reporting · 22 months
Healthcare · 2025Acute Care Bed Tower Baseline RebuildU.S. Southeast · Baseline development · 34 months
Healthcare · In progressAcademic Medical Campus Integrated Master ScheduleU.S. Northeast · Integrated master schedule · 60 months
Facing something like this?
Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.