Stadium Seating Bowl Rebuild Controls

A sixty-thousand-seat bowl rebuilt between seasons, with event dates the team cannot move.

Owner
Confidential
Region
U.S. Southwest
Market
Sports & Entertainment
Our role
Schedule risk and cost forecasting
Size
60,000 seats
Delivery
CM at-risk
Duration
36 months
Status
In progress · 2027
The challenge

What is at stake.

Demolition, precast seating and the new concourse have to fit between seasons. Material prices and precast plant capacity are uncertain, and the owner needs to know both the likely finish and the likely final cost.

Schedule36 monthsIn progress · finish 2027
2024202520262027
Today
Start
2024
Planned finish
2027
Time elapsed
64%
Our role

What we are doing.

Beck Franklin's role: schedule risk and cost forecasting. We advise and measure; the contractor builds.

01

Risk-based dates

We built a risk model that gives P50 and P80 dates for each season's handback.

02

Cost forecast

A monthly cost forecast ties each scope package to the schedule and to its contingency draw.

03

Precast tracking

Precast production at the plant is tracked against erection need dates every week.

04

Event constraints

Every scheduled event is a hard constraint, with readiness reviews before each.

Results

Where it stands.

P80Date reported for each season
MonthlyCost forecast to the owner
60,000Seats in the rebuild
36Months for the program

The events are fixed, so the risk has to be measured. We report both the date and the confidence behind it.

Risk and cost lead, Beck Franklin