Modular Data Center Rollout Reporting

Nine modular data center sites, three integrators and one executive report.

Owner
Confidential
Region
U.S. Southeast
Market
Data Centers
Our role
Program progress reporting
Size
9 sites
Delivery
Program delivery
Duration
22 months
Completed
2024
The challenge

What was at stake.

Each integrator reported progress its own way. Site leads said they were on track, but leadership could not compare sites or see which deliveries were at risk until a module missed its ship date.

Schedule22 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
22 mo
Our role

What we did.

Beck Franklin's role: program progress reporting. We advise and measure; the contractor builds.

01

Common milestones

We set a common milestone set for all sites: permit, pad, module ship, set, power, commission.

02

Same data date

All integrators reported on the same data date in the same format, every two weeks.

03

Factory visibility

Module fabrication status at the factory was tracked against each site's need date.

04

One executive page

Leadership received one page that compared every site and named the next risk.

Results

What the team delivered.

9Sites on one report
BiweeklyCommon data date
3Integrators reporting the same way
22Months, first site to last

Nine sites reported nine ways is no report at all. One format let leadership see the next problem early.

Program scheduler, Beck Franklin