Data Centers · U.S. Southwest

Hyperscale Data Hall Commissioning Controls

Four data halls where ready for service meant Level 5 integrated testing complete, not a finished building.

Owner
Confidential
Region
U.S. Southwest
Market
Data Centers
Our role
Commissioning-level scheduling
Size
4 halls · 72 MW
Delivery
CM at-risk
Duration
26 months
Completed
2025
The challenge

What was at stake.

The contractor schedule ended at substantial completion. Commissioning was shown as one bar per hall. The tenant's contract dates depended on integrated systems testing passing, and nobody could see how far along it was.

Schedule26 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
26 mo
Our role

What we did.

Beck Franklin's role: commissioning-level scheduling. We advise and measure; the contractor builds.

01

Commissioning in P6

We broke commissioning into Levels 1 to 5 for every hall, with each test tied to the equipment and systems it needed.

02

Test readiness

A weekly readiness report showed which tests were ready, blocked or failed, and why.

03

Hall by hall

Each hall was reported as its own path to ready for service, so one hall could not hide inside a campus average.

04

Tenant reporting

The owner shared a summary with the tenant each month based on the same data.

Results

What the team delivered.

4 of 4Halls ready on tenant dates
72 MWCommissioned
1,900Tests tracked in the schedule
26Months, notice to proceed to last hall

A data hall earns nothing until it passes integrated testing. We scheduled to that line, not to the building finish.

Mission critical scheduler, Beck Franklin