Commercial & Mixed-Use · U.S. Southeast

Mixed-Use Residential Block Delay Analysis

A residential and retail block where late design changes and a slow utility connection pushed completion out.

Owner
Confidential
Region
U.S. Southeast
Market
Commercial & Mixed-Use
Our role
Delay analysis and claims support
Size
420 units + retail
Delivery
CM at-risk
Duration
32 months
Completed
2025
The challenge

What was at stake.

The contractor claimed delay from owner design changes. The owner believed the utility connection, which the contractor managed, caused most of the slip. Rent and retail openings depended on the answer.

Schedule32 monthsCompleted 2025
202320242025
Start
2023
Finish
2025
Duration
32 mo
Our role

What we did.

Beck Franklin's role: delay analysis and claims support. We advise and measure; the contractor builds.

01

Schedule record

We reviewed the full schedule record, daily reports and correspondence.

02

Delay by event

Each event was analyzed for its effect on the critical path at the time it happened.

03

Value of delay

Delay days were assigned to each party, giving the owner a clear basis for negotiation.

04

Owner's position

The owner received a report it could use in negotiation and, if needed, in dispute.

Results

What the team delivered.

4Delay events analyzed
32Months of record reviewed
420Units in the block
SettledThrough negotiation

The owner needed to know which delay was theirs. The analysis gave them the answer and the reasons.

Forensic scheduler, Beck Franklin
Illustrative image
Commercial & Mixed-Use

Facing something like this?

Send us the schedule and the date that matters. We will tell you what is driving it and where you can still act. Repeat or similar projects qualify for our discounted Program Rate.