Manufacturing · U.S. Midwest

Heavy Equipment Factory Retool Recovery

A factory retool that fell behind while the old assembly line still had orders to fill.

Owner
Confidential
Region
U.S. Midwest
Market
Manufacturing
Our role
Schedule recovery
Size
480,000 SF retool
Delivery
Design-Build
Duration
16 months
Completed
2024
The challenge

What was at stake.

New tooling was late and foundation work found buried utilities. The plant could not shut down the old line until the new one was proven, and the original plan assumed a single cutover weekend.

Schedule16 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
16 mo
Our role

What we did.

Beck Franklin's role: schedule recovery. We advise and measure; the contractor builds.

01

Remaining work

We rebuilt the remaining schedule from a field walk, not from the last update.

02

Staged cutover

The single cutover was split into three stages, so production moved to the new line one cell at a time.

03

Daily tracking

During each cutover stage, progress was tracked daily against the plan with the plant manager.

04

Orders protected

Production planning used the recovery schedule to place orders on the line that would be running.

Results

What the team delivered.

0Missed customer shipments
3Cutover stages, each on time
16Months, start to full production
480,000 SFRetooled

The old line had to keep shipping. The recovery plan moved production a cell at a time so it could.

Recovery scheduler, Beck Franklin