Semiconductor · U.S. Pacific Northwest

Live Fab Process Exhaust Shutdown Schedule

Six process exhaust tie-ins inside an operating fab, each limited to a fixed shutdown window.

Owner
Confidential
Region
U.S. Pacific Northwest
Market
Semiconductor
Our role
Shutdown scheduling and reporting
Size
Live fab · 6 shutdowns
Delivery
CM at-risk
Duration
14 months
Completed
2024
The challenge

What was at stake.

Every hour of exhaust shutdown affects production. The fab released six windows over a year, each a few hours long, and any overrun would trip tools and scrap wafers.

Schedule14 monthsCompleted 2024
20232024
Start
2023
Finish
2024
Duration
14 mo
Our role

What we did.

Beck Franklin's role: shutdown scheduling and reporting. We advise and measure; the contractor builds.

01

Hour-by-hour scripts

Each tie-in was scheduled by the hour, with preparation, isolation, cut-in, test and restart.

02

Readiness gates

Materials, crews and permits were checked at a readiness gate one week before each window.

03

Live tracking

Progress during each shutdown was tracked live against the script with the fab operations lead.

04

Lessons applied

After each window, durations were corrected and the next script updated.

Results

What the team delivered.

6 of 6Windows closed on time
0Tool trips from overrun
14Months for the program
1 weekReadiness gate before each window

In a live fab, an overrun is measured in wafers. We scripted every window so there was none.

Shutdown scheduler, Beck Franklin