Decision windows: act while you still have options

Every schedule problem has a window when it is cheap to fix. The job of project controls is to show leadership that window before it closes.

June 2, 20264 min readBy Emmanuel Ugbaja, Principal & CEO

Every schedule problem has a moment when it is cheap to fix. A late submittal can be expedited before the fabricator’s slot is lost. A design question can be answered before the crew mobilizes. A resequence can be planned before the area is occupied. After that moment, the same problem costs more, and soon it costs the milestone.

Decision windows close quietly

Nobody announces that a window is closing. The submittal sits in review. The question waits for the next meeting. Float on the path shrinks a few days at a time. By the time the delay is obvious in the field, the cheap options are gone.

Show the window, not just the delay

Good project controls report more than what is late. They report which decisions are due, when each one must be made to protect the milestone, and what it costs to miss it. That turns a schedule report into an agenda.

  • The decision. Stated plainly, with who owns it.
  • The latest date to decide. Taken from the schedule logic and float, not from habit.
  • The cost of waiting. Days at the milestone, and what those days are worth.

The goal is to give clients enough visibility to make the hard decisions while they still have options.

Emmanuel Ugbaja, Principal & CEO

Price one late day with the Cost of Delay tool, or see how our executive reporting puts decision windows in front of leadership every month.

Discuss your project

Put this to work on your project.

Send the schedule and the date you are protecting. Beck Franklin will show you what is driving it.